Cadent Update

IMPORTANT UPDATE RECEIVED FROM CADENT
PHASE 3
Starts as planned on the 09th September [Main Street & Victoria Street Closed at the Junction with Greens Lane with 2 Way Temporary Traffic Signals Installed around Greens Lane onto Main Street] Still right turn only from Greens Lane and Left turn only from Nottingham Road.
We will then proceed with Phase 4 as planned on the 16th of September.
After ongoing discussions with the Local Highway Authority and Trent Barton Buses, we have mutually agreed to implement, at the same time as the road closure on Main Street / Nottingham Road, a ‘One-Way Closure’ on Newdigate Street/Road. This decision aims to reduce traffic congestion on nearby routes as much as reasonably possible while ensuring bus services for the community and schools can continue with minimal disruption.
Updated Project Details: PHASE 4
Start Date: Phase 4 – September 16th, 2024
Project Duration: 3 weeks
Traffic Management:
Road Closure [Main Street & Nottingham Road – Greens Lane to Broomhill Road]
One Way Traffic [Newdigate Street & Newdigate Road – Traffic Direction from Main Street to Main Road B600]
Diversion Route: Official diversion will be via Main Street | Eastwood Road | Gilt Hill | A610 | Nottingham Road | Kimberley Road | Nottingham Road.
Bus Diversions:
Route 34: Revised routes attached (from Trent Barton).
Route Rainbow One: Revised routes attached (from Trent Barton).
Route 27: No Affected during Phase 4.